Plan of action:

week 1 may 21 due date sprint 1 blockout finished and detail started

week 2 finish model first and second details

week 3 june 4 delivery- model completed with all final details and ready for textures/ hair cards applied?

week 4 textures begin, hair cards finish if need more time (or will be cut here if not feasible)

week 5 june 18 delivery textures continued, hopefully almost ndone

week 6 finished textures and ready for engine

week 7 june 30 delivery asset in engine and help wth rendering/posing

week 8 final adjustments 

weel 9 july 19 delivery

week 10

week 11 final delivery july 28





No comments:

Post a Comment

final submission project 3

 took extra renders of both projects for concisiveness in industry review